North Road Project (P059)

DESIGN & CONSTRUCT SERVICE ROADS ENHANCEMENT TO NORTH ROAD (P059)

November 2013 - November 2016 Project period62,000,000 QAR Contract value2013 - 2016 (multiple phases) Project duration

Project Overview

Project
DESIGN & CONSTRUCT SERVICE ROADS ENHANCEMENT TO NORTH ROAD (P059)
Client
PUBLIC WORKS AUTHORITY (ASHGAL)
Period
November 2013 - November 2016
Contractor
TEKFEN CONSTRUCTION
Subcontractor
GULF CONSTRUCTION COMPANY WLL
Subcontract Value
62,000,000 QAR

Work Description

Project delivery scope.

Construction & Installation of MSE Walls: Installation of 117,000 m² MSE Wall Earthworks including approximately 1.2 Million m³ Fill 200,000 m³ Excavation Works This major component of the North Road Project involved extensive construction of Mechanically Stabilized Earth (MSE) walls along the service roads. Our team handled all aspects from earthworks to final installation of the MSE wall systems. Project DESIGN & CONSTRUCT SERVICE ROADS ENHANCEMENT TO NORTH ROAD (P059) Client PUBLIC WORKS AUTHORITY (ASHGAL) Period November 2013 - November 2016 Contractor TEKFEN CONSTRUCTION Subcontractor GULF CONSTRUCTION COMPANY WLL Subcontract Value 28,000,000 QAR Work Description Provision of Material, Manpower & Machinery for MSE Wall Panel Precast Fabrication: 117,000 m² MSE Wall Panel Precast Fabrication Our precast facility manufactured all MSE wall panels required for the project, ensuring consistent quality and meeting the demanding project specifications and timelines. Project DESIGN & CONSTRUCT SERVICE ROADS ENHANCEMENT TO NORTH ROAD (P059) Client PUBLIC WORKS AUTHORITY (ASHGAL) Period November 2014 - November 2016 Contractor TEKFEN CONSTRUCTION Subcontractor GULF CONSTRUCTION COMPANY WLL Subcontract Value 13,500,000 QAR Work Description Precast of Parapets over MSE Wall Panels: We manufactured all precast parapet components designed to be installed atop the MSE walls, ensuring safety barriers met all regulatory requirements while maintaining aesthetic quality. Project DESIGN & CONSTRUCT SERVICE ROADS ENHANCEMENT TO NORTH ROAD (P059) Client PUBLIC WORKS AUTHORITY (ASHGAL) Period November 2014 - November 2016 Contractor TEKFEN CONSTRUCTION Subcontractor GULF CONSTRUCTION COMPANY WLL Subcontract Value 26,500,000 QAR Work Description Installation of Parapet over MSE Walls with Foundation: 21,000 m of parapet installation Our team installed the precast parapets along the entire length of the MSE walls, including all necessary foundation work to ensure structural integrity and long-term durability.

Project Gallery

North Road Project - Aerial View
North Road Project - Construction Phase
North Road Project - Workers on Site
North Road Project - Concrete Barriers
North Road Project - Completed Section
North Road Project - Completed Section