Home / Projects / Al Bustan Street South

Al Bustan Street South Expansion Project

Project Overview

Project

AL BUSTAN STREET SOUTH

Client

PUBLIC WORKS AUTHORITY (ASHGAL)

Period

May 2019 - September 2020

Contractor

Hyundai Engineering & Construction Co., Ltd.

Subcontractor

Gulf Construction Company. W.L.L

Subcontract Value

USD 35,80,000.00

Work Description

  • Construction of MSE Walls & Counter Balance Slabs
  • Precast Fabrication & Installation of MSE Walls (14,000 m²)
  • Filling Works to MSE Walls (195,000 m³)
  • Construction of Counter Balance Slabs (6,000 m)

Gulf Construction executed MSE wall construction (14,000m²) and counter balance slabs (6,000m) for Al Bustan Street South, including 195,000m³ of filling works for Ashgal. The 16-month project (May 2019-Sept 2020) was valued at 13M QAR.

Project Summary

Location

Al Bustan Street South, Qatar

Project Type

Road Infrastructure

Duration

16 months (May 2019 - Sep 2020)

Key Quantities

  • 14,000 m² MSE Walls
  • 195,000 m³ Filling
  • 6,000 m Counter Balance Slabs

Need Infrastructure Services?

Our team specializes in road and infrastructure projects. Contact us to discuss your requirements.

Contact Us

Project Gallery

MSE Wall Installation
Precast Fabrication