The North Field East Expansion EPC-1 Project is part of Qatar's efforts to significantly increase its liquefied natural gas (LNG) production capacity. This major expansion aims to reinforce Qatar's position as the world’s top LNG exporter.
North Field East EPC-1 Project
QATAR ENERGY
May 2022 - November 2022
Chiyoda-Technip Joint Venture (CTJV)
Tekfen Construction and Installation Co., Inc.
Gulf Construction Company. W.L.L
2,694,166 USD
Gulf Construction Company executed the $2.7 million North Field East Expansion EPC-1 project for Qatar Energy, constructing piperack foundations/sockets and fabricating precast beams/columns from May to November 2022
North Field, Qatar
Energy Infrastructure Expansion
6 months (May 2022 - Nov 2022)
Our team specializes in complex energy projects. Contact us to discuss your requirements.