Project delivery / Haskoch Group

The North Road Project

The North Road Project focused on the development of a significant highway connecting Doha to the northern areas of Qatar, particularly towards Al Shamal and Al Khor. It involved the construction of a dual carriageway and was part of efforts to improve access and mobility between Doha and the northern regions.

October 2010 - December 2013 Project periodUSD 10,10,000.00 Contract value2010 - 2013 Project duration

Project Overview

Project
The North Road Project
Client
PUBLIC WORKS AUTHORITY (ASHGAL)
Period
October 2010 - December 2013
Contractor
Tekfen Construction and Installation Co., Inc.
Subcontractor
Gulf Construction Company. W.L.L
Subcontract Value
USD 10,10,000.00

Work Description

Project delivery scope.

Supply & Application of Protective Coating Works & Waterproofing Membrane: 80,000 m² Protective Coating 15,000 m² Membrane works 23 Bridges 10 Underpasses 12 km Barriers This extensive protective coating project covered critical infrastructure elements along The North Road Corridor Enhancement Project Corridor Enhancement Project corridor. Our team applied specialized coatings and waterproofing membranes to ensure long-term protection against environmental factors, significantly extending the lifespan of these structures.

Project Gallery

The North Road Corridor Enhancement Project Corridor Enhancement Project Project - Aerial View
The North Road Corridor Enhancement Project Corridor Enhancement Project Project - Construction Phase
The North Road Corridor Enhancement Project Corridor Enhancement Project Project - Workers on Site
The North Road Corridor Enhancement Project Corridor Enhancement Project Project - Completed Section
The North Road Corridor Enhancement Project Corridor Enhancement Project Project - Completed Section