Project delivery / Haskoch Group
The North Road Corridor Enhancement Project
The North Road Corridor Enhancement Project, overseen by Qatar's Public Works Authority (Ashghal), is a significant infrastructure initiative aimed at upgrading the Al Shamal Road—one of the country's primary highways connecting Doha to northern regions such as Al Shamal and Al Khor.
Project Overview
- Project
- The North Road Corridor Enhancement Project
- Client
- PUBLIC WORKS AUTHORITY (ASHGAL)
- Period
- November 2014 - November 2016
- Contractor
- Tekfen Construction and Installation Co., Inc.
- Subcontractor
- Gulf Construction Company. W.L.L
- Subcontract Value
- USD 73,00,000.00
Work Description
Project delivery scope.
Installation of Parapet over MSE Walls with Foundation: 21,000 m of parapet installation Our team installed the precast parapets along the entire length of the MSE walls, including all necessary foundation work to ensure structural integrity and long-term durability.
Site progress
Project gallery
04 frames — select to enlarge