Construction of New Interchange IC3 at Ras Bufontas Free Zone (Project P042)

Project Overview

Project

Construction Of New Interchange IC3 at Ras Bufontas Free Zone – P042

Client

Public Work Authority (Ashgal)

Period

November 2020 - December 2021

Contractor

Joint Venture between Redco International and PORR Qatar

Subcontractor

Gulf Construction Company. W.L.L

Subcontract Value

USD 38,50,000.00

Work Description

Earth filling to MSE Walls & Roads including:

  • Fill material preparation
  • Construction of Counter Balance Slab
  • Parapets installation
  • Kerbstone and paving block works
  • Utilities installation

Key Quantities

  • Earth Filling: 450,000 cubic meters
  • MSE Wall Installation: 19,500 square meters
  • Construction of Counter Balance Slab: 2,600 linear meters

This major interchange project at Ras Bufontas Free Zone involved extensive earthworks and construction of mechanically stabilized earth (MSE) walls to support the new interchange structure. Our scope included all preparatory work for the fill materials, construction of critical structural elements like counter balance slabs, and installation of finishing elements including parapets, kerbstones, and paving blocks.

Project Summary

Location

Ras Bufontas Free Zone, Qatar

Project Value

USD 38,50,000.00

Duration

13 months (Nov 2020 - Dec 2021)

Key Components

  • Massive earthworks
  • MSE Wall construction
  • Structural concrete works
  • Road finishing elements
  • Utilities installation

Need Road Construction Services?

Our team has extensive experience in major interchange projects. Contact us to discuss your requirements.

Contact Us

Project Gallery

IC3 Interchange Construction Phase 1
IC3 Interchange Earthworks