Project delivery / Haskoch Group
Design & Build of the Ras Bufontas Walkway at Ras Bufontas Free Zone
The Ras Bufontas Walkway project involves the creation of a scenic, pedestrian-friendly beachfront promenade within the Ras Bufontas Free Zone, enhancing the zone's recreational and sustainable features. The walkway is designed to accommodate foot traffic, cyclists, and individuals seeking a pleasant outdoor space with views of the sea.
Project Overview
- Project
- Walkway – Earthwork with Embankment and Carpark Subgrade Earthworks
- Client
- Qatar Free Zone Authority (QFZA)
- Period
- January 2022 - November 2022
- Contractor
- PORR Qatar Construction W.L.L.
- Subcontractor
- Gulf Construction Company. W.L.L
- Subcontract Value
- USD 9,62,000.00
Work Description
Project delivery scope.
Construction of Embankment for Walkways and Car Parks including: Supply & Filling by Selected Fill Materials (135,000 m³) Engineering fill preparation Subgrade fill preparation Selected fill placement Wash Sand and Dune Sand application All related civil works This earthwork project involved comprehensive preparation of walkways and car park areas within the Qatar Free Zone. Our scope included all earthwork operations from material supply through to final grading, ensuring proper compaction and subgrade preparation for subsequent construction phases. The project was completed on schedule despite the challenges of working with various fill materials.
Site progress
Project gallery